A program manager must communicate a significant scope reduction to stakeholders who had high expectations. What communication approach is most effective?
-
A
Send a brief email and avoid follow-up questions
-
B
Present the change in a formal meeting, explain rationale, and invite discussion
-
C
Delegate the communication to component project managers
-
D
Announce it only to the sponsor and let information cascade informally