CPL CPL Budget & Resource Management 1 — Questions and Answers
Question 1: Which budgeting approach in program management starts from zero each period, requiring all expenses to be justified rather than carrying forward prior allocations?
- Incremental budgeting
- Zero-based budgeting (Correct answer)
- Activity-based budgeting
- Rolling wave budgeting
Correct answer: Zero-based budgeting
Zero-based budgeting requires every line item to be justified from scratch each budget cycle, preventing automatic carryover of prior-period spending.
Question 2: A program manager notices that the cost performance index (CPI) for a major project component is 0.82. What does this indicate?
- The project is under budget
- The project is on budget
- The project is over budget (Correct answer)
- The project has no cost variance
Correct answer: The project is over budget
A CPI below 1.0 means the program is spending more than planned for the work completed, indicating an over-budget condition.
Question 3: Resource leveling in program management is primarily used to:
- Increase the total program budget
- Resolve resource over-allocation by adjusting the schedule (Correct answer)
- Reduce the number of team members required
- Eliminate all schedule float
Correct answer: Resolve resource over-allocation by adjusting the schedule
Resource leveling adjusts start and finish dates to resolve resource conflicts and over-allocation, often extending the overall schedule.
Question 4: In a program, which document formally authorizes the program manager to apply organizational resources to program activities?
- The program scope statement
- The program charter (Correct answer)
- The benefits realization plan
- The resource management plan
Correct answer: The program charter
The program charter formally authorizes the program and grants the program manager authority to apply resources to achieve program objectives.
Question 5: Which technique estimates future program costs by using a statistical relationship between historical data and other variables?
- Analogous estimating
- Bottom-up estimating
- Parametric estimating (Correct answer)
- Three-point estimating
Correct answer: Parametric estimating
Parametric estimating uses statistical relationships (e.g., cost per unit) derived from historical data to calculate cost or duration estimates.
Question 6: A program manager must allocate a shared technical specialist across three concurrent projects. What is the most appropriate resource management strategy?
- Assign the specialist full-time to the highest-priority project only
- Use a resource matrix to schedule the specialist's time across all three projects (Correct answer)
- Hire a contractor to replace the specialist on the lower-priority projects
- Delay all three projects until the specialist is fully available
Correct answer: Use a resource matrix to schedule the specialist's time across all three projects
A resource matrix (RACI or resource assignment matrix) helps formally schedule and communicate the shared specialist's availability across all competing projects.
Which budgeting approach in program management starts from zero each period, requiring all expenses to be justified rather than carrying forward prior allocations?