A program manager discovers that two key stakeholders have conflicting priorities that are causing delays. What is the BEST first step?
-
A
Escalate immediately to the program sponsor
-
B
Facilitate a joint meeting to surface and align conflicting interests
-
C
Side with the stakeholder who has more authority
-
D
Document the conflict and wait for it to resolve naturally