When a program manager implements a workaround, it is a response to:
-
A
A risk that has been accepted with a passive strategy
-
B
An issue that was not anticipated and has no prior contingency plan
-
C
A risk that has been transferred to a third party
-
D
A risk that has been fully mitigated in advance