Which project management document breaks down the total project scope into smaller, manageable components and serves as the foundation for scheduling and cost estimating?
-
A
Project Charter
-
B
Risk Register
-
C
Work Breakdown Structure (WBS)
-
D
Responsibility Assignment Matrix (RAM)