During a road resurfacing project, the inspector discovers that the contractor's schedule shows a 10-day float on a critical paving activity. What does this indicate?
-
A
The activity has no scheduling flexibility
-
B
The activity can be delayed up to 10 days without affecting project completion
-
C
The activity is behind schedule by 10 days
-
D
The activity requires 10 additional days of resources