Under OSHA's Lockout/Tagout (LOTO) standard 29 CFR 1910.147, which action must be performed FIRST before servicing energized equipment?
-
A
Notify all affected employees
-
B
Apply a lockout device to the energy isolating device
-
C
Verify zero energy state with a test instrument
-
D
Shut off the equipment using the normal stopping procedure