An installer discovers unexpected site conditions (e.g., existing buried conduit) after the bid is awarded. What is the appropriate course of action?
-
A
Absorb the extra cost to avoid conflict
-
B
Notify the customer and submit a change order for differing site conditions
-
C
Stop work immediately and leave the site
-
D
Hire additional labor without authorization