A contract manager discovers that a subcontractor has submitted invoices with inflated labor hours. What is the FIRST ethical obligation?
-
A
Ignore it to preserve the subcontractor relationship
-
B
Report the discrepancy through proper internal channels immediately
-
C
Negotiate a private settlement with the subcontractor
-
D
Approve the invoices and adjust future payments