  1. Under the Changes clause in a government contract, which party has the unilateral right to direct changes within the general scope of the contract?

    Answer: The contracting officer

    The contracting officer holds the unilateral authority to direct changes within the scope of the contract under the Changes clause.

  2. A bilateral contract modification that changes the contract price, delivery schedule, or terms with the consent of both parties is called a:

    Answer: Supplemental agreement

    A supplemental agreement is a bilateral modification that requires mutual consent and is used to alter substantive contract terms.

  3. Which type of contract modification does NOT require the contractor's signature?

    Answer: Administrative change

    Administrative changes, such as updating a contracting officer's address or administrative data, are unilateral and do not require the contractor's signature.

  4. A constructive change occurs when:

    Answer: Government actions or inactions force the contractor to perform work beyond the contract scope without formal authorization

    A constructive change is an informal change resulting from government conduct—actions or inactions—that effectively requires extra work without a formal written change order.

  5. When a contract modification results in work that falls entirely outside the original contract's general scope, this is referred to as a:

    Answer: Cardinal change

    A cardinal change is one so drastic that it alters the essential nature of the contract, potentially allowing the contractor to treat it as a breach rather than a modification.

  6. Under FAR Part 43, which of the following is NOT a proper reason for issuing a unilateral change order?

    Answer: Negotiating a price increase for changed work

    Negotiating a price increase requires bilateral agreement and cannot be accomplished through a unilateral change order.

  7. What is the primary purpose of an equitable adjustment in a modified government contract?

    Answer: To restore the contractor to the same financial position they would have been in had the change not occurred

    An equitable adjustment restores the contractor to the same economic position they would have been in absent the change, covering increased costs and a reasonable profit.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ncmahq.org — Test delivery, exam format, passing score, renewal, retake policy, score release, time limit, score validity, fees, test dates · verified Oct 2026
Certified Professional Contract Manager: Contract Modifications and Change Management Flashcards — CPCM Study Cards with Answers