Contract Performance and Administration Flashcards
6 cards from real CPCM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Contract Performance and Administration flashcards as text
What is the primary purpose of a Contractor Performance Assessment Reporting System (CPARS) evaluation?
Answer: To document contractor past performance for future source selections
CPARS evaluations create an official record of contractor performance that source selection officials consult when evaluating past performance in future procurements.
A cure notice is issued to a contractor when:
Answer: The contractor's failure to perform endangers timely contract completion
FAR 49.607 requires a cure notice when contract performance is endangered, giving the contractor at least 10 days to cure the problem before a termination for default.
What distinguishes a 'show cause' notice from a 'cure notice'?
Answer: A show cause notice is issued when the contractor has already failed to meet a delivery date and default termination is being considered
A show cause notice is issued after a delivery failure has already occurred and asks the contractor to explain why the contract should not be terminated for default.
Which of the following is an example of government-furnished equipment (GFE) risk in contract administration?
Answer: Government delays delivery of GFE causing contractor schedule slippage
When the government fails to provide GFE on time, the contractor may have a valid excusable delay or even a breach of contract claim, shifting schedule risk to the government.
Under FAR 52.246, a first-article test (FAT) is designed to:
Answer: Verify that the contractor can produce items meeting contract requirements before full production begins
First-article testing verifies production processes and materials before committing to full production, reducing the risk of large-scale nonconformance.
Which metric measures the cost efficiency of work performed in Earned Value Management?
Answer: Cost Performance Index (CPI)
The Cost Performance Index (CPI) = Earned Value ÷ Actual Cost; a CPI below 1.0 means the project is spending more than the value of work accomplished.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy