Contract Closeout and Termination Flashcards
6 cards from real CPCM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Contract Closeout and Termination flashcards as text
Which of the following is the primary difference between termination for default and termination for convenience?
Answer: Termination for convenience compensates the contractor for costs incurred plus reasonable profit, while default may result in reprocurement cost liability for the contractor
Under termination for convenience (FAR 49.2), the contractor recovers costs plus a reasonable profit; under default (FAR 49.4), the contractor may owe the government excess reprocurement costs.
The statute of limitations for a contractor to file a claim under the Contract Disputes Act (CDA) is:
Answer: 6 years from the date the claim accrued
The CDA imposes a 6-year statute of limitations running from the date the claim accrued, meaning the date the contractor knew or should have known the basis for the claim.
What is the purpose of a release of claims in a contract closeout?
Answer: To document the contractor's waiver of any further claims against the government for contract performance
A release of claims is a bilateral agreement in which the contractor agrees that the final payment settles all outstanding issues, releasing the government from further claims.
Under the Contract Disputes Act (CDA), a contracting officer's final decision (COFD) must be issued within what timeframe for claims not exceeding $100,000?
Answer: 60 days of receipt of a written request for a final decision
FAR 33.211 requires the contracting officer to issue a final decision within 60 days for claims of $100,000 or less when the contractor requests an expedited decision.
Which of the following actions must be completed before a contract can be officially closed out?
Answer: All deliverables accepted, final invoice paid, and all open actions (audits, property disposal) resolved
Contract closeout requires confirming delivery/acceptance, resolving all financial and property matters, completing audits, and processing the final payment before the file is closed.
Excess reprocurement costs in a termination for default are:
Answer: Costs the government incurs to complete the work through another contractor, charged back to the defaulted contractor
If the government must reprocure after a default termination, the defaulted contractor is liable for the difference between the defaulted contract price and the cost of reprocurement.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy