← All CPCM Flashcard Decks

Contract Closeout and Termination Flashcards

6 cards from real CPCM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Contract Closeout and Termination flashcards as text
  1. Which board or court has jurisdiction over contractor appeals of contracting officer final decisions under the Contract Disputes Act?

    Answer: Armed Services Board of Contract Appeals (ASBCA), Civilian Board of Contract Appeals (CBCA), or U.S. Court of Federal Claims

    Under the CDA, contractors may appeal to the appropriate Board of Contract Appeals (ASBCA or CBCA) or directly to the U.S. Court of Federal Claims within 12 months of the COFD.

  2. A convenience termination settlement proposal should include which of the following?

    Answer: Costs incurred, settlement expenses, and a reasonable profit on work performed prior to termination

    A termination for convenience settlement covers allowable costs incurred before termination plus settlement expenses and a fair profit on the work done, but not anticipated profits on unperformed work.

  3. The quick-closeout procedure under FAR 42.708 is used when:

    Answer: Final audit of indirect rates is not yet complete but negotiating a rate now is cost-effective

    Quick-closeout allows the ACO to negotiate final indirect rates directly with the contractor when the cost of waiting for a DCAA audit outweighs the benefit, expediting file closure.

  4. In a termination for default, what must the government prove to sustain the default?

    Answer: The contractor failed to perform a material contract requirement and the default was not excusable

    To sustain a default termination, the government must show a material failure to perform and that the failure was not caused by excusable delays under FAR 49.401.

  5. What happens to a default termination that the government later determines was improper?

    Answer: It is automatically converted to a termination for convenience

    An improper default termination is converted to a termination for convenience by operation of law, entitling the contractor to a convenience settlement rather than default recovery.

  6. Records retention requirements for closed government contracts generally require files to be kept for:

    Answer: 6 years and 3 months after final payment for most contract files

    FAR 4.805 requires most contract files to be retained for 6 years and 3 months after final payment, ensuring availability for audits and litigation.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ncmahq.org — Test delivery, exam format, passing score, renewal, retake policy, score release, time limit, score validity, fees, test dates · verified Oct 2026