  1. A contract manager discovers that a sole-source vendor is consistently delivering late. What is the BEST first step?

    Answer: Issue a cure notice requesting corrective action within a defined timeframe

    A cure notice formally notifies the vendor of deficiencies and provides an opportunity to correct performance before escalation.

  2. Which procurement strategy is MOST appropriate when the government needs a vendor to invest heavily in specialized infrastructure?

    Answer: Cost-plus-incentive-fee contract

    Cost-plus-incentive-fee contracts share risk and reward between buyer and seller, encouraging vendor investment in specialized capabilities.

  3. What does 'vendor segmentation' primarily help a contract manager accomplish?

    Answer: Prioritize resources and relationship strategies based on vendor criticality

    Vendor segmentation classifies suppliers by strategic importance, allowing tailored relationship management and resource allocation.

  4. In a competitive procurement, a vendor submits a bid that is significantly below all other offers. The contract manager should FIRST:

    Answer: Request a price/cost analysis to verify the bid is realistic

    An unusually low bid may indicate unrealistic pricing, so a price/cost analysis helps determine if the offer is responsible before award.

  5. Which clause protects the buyer if a contractor fails to complete work by the agreed delivery date?

    Answer: Liquidated damages clause

    A liquidated damages clause pre-establishes the amount the contractor owes the buyer for each day of delay.

  6. A 'make-or-buy' analysis in procurement strategy is used to determine:

    Answer: Whether to produce goods/services internally or outsource them

    Make-or-buy analysis compares the cost, capability, and strategic value of in-house production versus outsourcing.

  7. Under the FAR, what is the primary purpose of Past Performance evaluations in source selection?

    Answer: To predict the likelihood of successful contract performance based on prior history

    Past performance evaluations assess how well a vendor has performed on prior contracts to predict future performance.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ncmahq.org — Test delivery, exam format, passing score, renewal, retake policy, score release, time limit, score validity, fees, test dates · verified Oct 2026