  1. Under the Changes clause, a contractor must submit a proposal for an equitable adjustment within how many days of receiving a change order, unless the contracting officer specifies otherwise?

    Answer: 30 days

    FAR 52.243-1 requires the contractor to assert its right to an equitable adjustment within 30 days of receiving the change order.

  2. Which of the following best describes a value engineering change proposal (VECP)?

    Answer: A contractor-initiated proposal to change a requirement in a way that reduces cost while maintaining required performance

    A VECP is voluntarily submitted by the contractor proposing changes to reduce contract cost while maintaining required performance, with savings shared between the government and contractor.

  3. When a change order is issued and the cost impact cannot be agreed upon before work must begin, the contract may include a:

    Answer: Undefinitized contract action (UCA)

    An undefinitized contract action allows work to begin before price is agreed upon, with definitization required within a set timeframe.

  4. The 'Changes' clause in a fixed-price contract typically covers changes in all of the following EXCEPT:

    Answer: Profit percentage

    The Changes clause covers technical and delivery-related changes; profit percentage adjustments are part of equitable adjustment negotiations, not a direct change category.

  5. A contractor who believes the government has issued a constructive change should:

    Answer: Perform the work and submit a claim within the applicable statute of limitations

    The contractor should perform the work to avoid default and then submit a claim for equitable adjustment, as refusing to work could be considered a breach.

  6. What distinguishes a 'change in scope' from a 'change within scope' in contract modification?

    Answer: A change in scope alters what was bargained for in the original contract; a change within scope falls within what the parties anticipated

    A change within scope is one the parties implicitly agreed the government could order; a change in scope exceeds those implied parameters and may constitute a cardinal change.

  7. Which document is typically used by a contractor to formally propose a change to contract specifications, drawings, or design?

    Answer: Engineering Change Proposal (ECP)

    An Engineering Change Proposal (ECP) is the formal document a contractor submits to propose changes to technical specifications, drawings, or design requirements.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ncmahq.org — Test delivery, exam format, passing score, renewal, retake policy, score release, time limit, score validity, fees, test dates · verified Oct 2026