Which of the following best describes the 'quantity takeoff' process in construction estimating?
-
A
Negotiating final costs with the owner
-
B
Measuring and listing all materials and work items from project drawings
-
C
Selecting the lowest subcontractor bid
-
D
Reviewing the project schedule for delays