Which of the following best describes the 'quantity takeoff' process in construction estimating?
Select your answer
A
Negotiating final costs with the owner
B
Measuring and listing all materials and work items from project drawings
C
Selecting the lowest subcontractor bid
D
Reviewing the project schedule for delays