A risk manager is evaluating two controls for the same risk: Control A reduces likelihood by 70% at a cost of $50K; Control B reduces impact by 80% at a cost of $200K. Which factor should MOST influence the selection?
-
A
Always choose the control with the highest percentage reduction
-
B
The nature of the risk โ whether preventing occurrence or limiting damage is more valuable
-
C
Regulatory preference for likelihood-based controls
-
D
The number of employees who will interact with each control