The COR receives a contractor invoice that includes charges for work the COR did not observe being performed. What is the CORRECT action?
-
A
Approve the invoice since the contractor is responsible for its accuracy
-
B
Withhold approval and notify the CO of the discrepancy pending investigation
-
C
Reject the entire invoice immediately without notifying the CO
-
D
Ask the contractor to resubmit with corrected amounts independently