The 'cardinal change' doctrine is significant because it means:
-
A
The CO approved an out-of-scope change without competition
-
B
A change so drastic it falls outside the original contract scope, potentially allowing the contractor to treat it as a breach
-
C
A change was made without proper FAR authority
-
D
The modification exceeded the simplified acquisition threshold