Under FAR Part 15, when is a contractor required to submit certified cost or pricing data?
-
A
When the contract exceeds the Simplified Acquisition Threshold
-
B
When the negotiated contract action exceeds the TINA threshold
-
C
Whenever a sole-source contract is awarded regardless of value
-
D
When the contracting officer requests it regardless of contract value