Under a Time-and-Materials (T&M) contract, what is the government's primary financial risk?
-
A
The contractor may underperform without penalty since profit is fixed
-
B
Costs can escalate indefinitely if hours worked exceed the estimate
-
C
The ceiling price can be exceeded without a contract modification
-
D
The government pays a fixed price regardless of actual hours worked