Government-Furnished Property & Equipment Flashcards
7 cards from real COR practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Government-Furnished Property & Equipment flashcards as text
Which of the following is NOT a type of Government property as defined in FAR Part 45?
Answer: Contractor's commercial tooling used exclusively on a Government contract
Contractor-owned commercial tooling used on a Government contract remains contractor property and is not classified as Government property under FAR Part 45.
A contractor's property management system must include all of the following elements EXCEPT:
Answer: Contractor's profit and loss statements for GFP usage
A contractor's property management system addresses acquisition, records, physical inventory, and other stewardship controls, but does not include financial profit/loss statements for GFP.
How often must contractors typically conduct a physical inventory of Government property?
Answer: Annually or as required by contract terms
FAR 52.245-1 requires contractors to conduct physical inventories of Government property at least annually or as otherwise specified in the contract.
When the COR observes a contractor using Government-Furnished Equipment for work NOT covered under the contract, what should the COR do?
Answer: Document the observation and report it to the contracting officer for appropriate action
The COR should document the unauthorized use and report it to the contracting officer, who has the authority to take corrective action.
Government-Furnished Material (GFM) differs from Government-Furnished Equipment (GFE) primarily in that GFM is:
Answer: Material intended to be incorporated into or consumed during contract performance, not reused after contract end
GFM is material consumed or incorporated into the end product during performance, while GFE is equipment expected to be returned or transferred after contract completion.
Which agency is responsible for approving a contractor's property management system under DCSA/DCMA oversight?
Answer: The Defense Contract Management Agency (DCMA)
DCMA is responsible for reviewing and approving contractor property management systems as part of their contract administration and oversight function.
What is 'Contractor-Acquired Property' (CAP) in the context of Government contracts?
Answer: Property acquired by the contractor under a contract in which the Government has title or will acquire title upon contract completion
CAP is property purchased by a contractor using contract funds where title vests in the Government, making it subject to the same FAR Part 45 property management requirements as GFP.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- fai.gov — Renewal, test delivery, eligibility, exam information · verified Nov 2026