In quantitative risk analysis, 'Expected Monetary Value' (EMV) is calculated as:
-
A
Risk impact minus risk probability
-
B
Probability of occurrence multiplied by the financial impact
-
C
Total project cost divided by number of risks
-
D
Maximum potential loss plus mitigation costs