A stakeholder requests a significant change to project scope after the project has begun. What is the correct first step?
-
A
Implement the change immediately to satisfy the stakeholder
-
B
Evaluate the change impact and submit it through the change control process
-
C
Reject the change since scope is already defined
-
D
Update the project charter to include the new scope