Preventive Maintenance Schedules Flashcards
7 cards from real CNC practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Preventive Maintenance Schedules flashcards as text
When performing a weekly PM on a CNC machining center, which coolant system check is most critical?
Answer: Check coolant concentration using a refractometer
Coolant concentration directly affects tool life and corrosion protection, and should be verified weekly with a refractometer.
A CNC lathe PM schedule calls for checking the chuck jaw repeatability. What instrument is used for this task?
Answer: Dial test indicator
A dial test indicator measures runout and positional repeatability of chuck jaws during PM checks.
Which lubricant type is typically specified for CNC ball screw assemblies during scheduled PM?
Answer: Low-viscosity grease such as NLGI #2
Ball screws require NLGI #2 grease applied in controlled amounts to prevent over-lubrication and contamination.
During a monthly PM inspection, a technician finds the CNC machine's air pressure regulator is set at 85 PSI instead of the required 100 PSI. What is the most likely consequence if left uncorrected?
Answer: Inadequate clamping force on pneumatic fixtures
Insufficient air pressure reduces clamping force on pneumatic workholding, risking part movement during cutting.
What is the purpose of checking the Z-axis counterbalance during a CNC vertical machining center PM?
Answer: To ensure the spindle head is properly supported against gravity at rest
The Z-axis counterbalance supports the spindle head weight so the Z-axis servo is not overloaded when the axis is stationary.
A PM checklist requires inspecting the CNC control cabinet filters. How often are these filters typically cleaned or replaced?
Answer: Monthly or per manufacturer specification based on environment
Control cabinet air filters trap dust that can cause overheating; cleaning frequency depends on the shop environment but is generally monthly.
During a PM procedure, the technician notices the machine tool way covers (telescoping steel covers) are dented and not sliding freely. What is the primary risk if this is ignored?
Answer: Chips and coolant contaminating the linear guideways
Damaged way covers allow chips and coolant to reach the linear guides, causing accelerated wear and premature failure.