Financial Analysis & Energy Performance Contracting Flashcards
7 cards from real CMVP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Financial Analysis & Energy Performance Contracting flashcards as text
What is a Power Purchase Agreement (PPA) in the context of on-site energy generation?
Answer: An agreement where a third party owns and operates generation equipment and sells the output to the host site at an agreed rate
In a PPA, a third-party developer owns, operates, and maintains the generation system (e.g., solar) and sells the electricity produced to the host customer at a predetermined rate, often below retail utility rates.
In financial analysis of energy projects, 'cost avoidance' differs from 'cost savings' in that:
Answer: Cost avoidance represents the value of not incurring costs that would have been incurred without the project
Cost avoidance is the value of expenditures prevented by an efficiency measure (e.g., avoiding a rate increase), while cost savings are reductions in actual expenditures compared to the established baseline.
When establishing the financial baseline for an EPC, which factor is most critical to document accurately?
Answer: Pre-retrofit energy consumption and cost data reflecting normal operations
The pre-retrofit baseline must accurately capture normal operational energy use and costs so that savings can be measured against a defensible reference point throughout the contract.
What is the typical role of an independent third-party M&V agent in an EPC?
Answer: To provide unbiased verification of savings calculations, protecting both the client and ESCO
An independent M&V agent provides objective, unbiased verification of savings, which protects both parties by ensuring that reported savings are accurate and agreed measurement protocols are followed.
Life Cycle Cost Analysis (LCCA) in energy project evaluation considers:
Answer: All costs and savings over the project's life, including capital, operations, maintenance, and energy
LCCA evaluates the total cost of ownership over a project's lifespan, encompassing initial investment, ongoing O&M costs, energy savings, and residual value to determine overall cost-effectiveness.
In EPC financial modeling, what is the purpose of a sensitivity analysis?
Answer: To assess how changes in key assumptions (energy prices, savings rates) affect project financial outcomes
Sensitivity analysis tests how variations in uncertain inputs — such as future energy prices, occupancy, or savings estimates — impact key financial metrics like NPV and IRR, revealing project risk.
An adjustment clause in an EPC is used to:
Answer: Modify the baseline or savings calculations to account for changes in operating conditions from the baseline period
Adjustment clauses (or 'baseline adjustments') reconcile the measurement baseline to reflect changes in occupancy, production, weather, or equipment use that differ from baseline conditions, ensuring fair savings attribution.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- aeecenter.org — Test delivery, eligibility, exam dates, fees, exam format, retake fee, retake policy, score release, score validity, time limit · verified Oct 2026