Maintenance Planning and Scheduling Flashcards

7 cards from real CMRT practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Maintenance Planning and Scheduling flashcards as text
  1. What is the primary purpose of a work order in a maintenance management system?

    Answer: To document, authorize, and track maintenance work from initiation to completion

    A work order is the central document that authorizes, tracks, and records all details of a maintenance job including labor, materials, and cost.

  2. What does the acronym CMMS stand for in the context of maintenance management?

    Answer: Computerized Maintenance Management System

    CMMS stands for Computerized Maintenance Management System, a software platform used to manage work orders, assets, inventory, and maintenance schedules.

  3. A maintenance planner is developing a job plan for replacing a pump seal. Which element is MOST critical to include in the job plan?

    Answer: A detailed list of required materials, tools, and step-by-step task instructions

    A comprehensive job plan must include materials, tools, safety requirements, and step-by-step procedures so the technician can execute the work efficiently without interruption.

  4. In maintenance planning, what does 'wrench time' measure?

    Answer: The time technicians spend actively performing hands-on maintenance work

    Wrench time (also called tool time) measures the percentage of a technician's day actually spent performing direct maintenance work, excluding travel, waiting, and administrative tasks.

  5. What is the recommended target range for a healthy maintenance work order backlog?

    Answer: 2 to 4 weeks of available crew work

    A backlog of 2 to 4 weeks of crew work is generally considered healthy — enough work to keep crews busy and allow efficient scheduling without becoming unmanageable.

  6. Which of the following BEST describes the difference between a maintenance planner and a maintenance scheduler?

    Answer: The planner determines what work needs to be done and how; the scheduler determines when and who will do it

    The planner defines the scope, materials, tools, and procedures for a job (the 'how'), while the scheduler coordinates timing, crew assignment, and sequencing (the 'when and who').

  7. What is a maintenance 'shutdown' or 'turnaround' primarily used for?

    Answer: Performing major inspections, overhauls, and capital work that cannot be done while equipment is running

    Shutdowns/turnarounds are planned outage events where major maintenance, inspections, and upgrades are concentrated because the work requires equipment to be offline.