Preventive & Predictive Maintenance Flashcards
7 cards from real CMM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Preventive & Predictive Maintenance flashcards as text
On the P-F curve, what does the interval between point P and point F represent?
Answer: The time between a detectable potential failure and functional failure
The P-F interval is the warning window between when a failure becomes detectable (P) and when the asset can no longer perform its function (F).
As a general rule, how often should a condition-monitoring inspection be performed relative to the P-F interval?
Answer: At an interval shorter than the P-F interval, often about half of it
Inspecting at less than the P-F interval (commonly half) ensures the developing failure is caught before it becomes functional.
Which predictive technology is best suited for detecting loose or overheated electrical connections in a switchgear panel?
Answer: Infrared thermography
Loose or corroded connections create resistance and heat, which infrared cameras detect without contact.
Vibration analysis on a centrifugal pump shows a dominant peak at 1x running speed in the radial direction. What is the most likely cause?
Answer: Rotor imbalance
Imbalance typically produces a strong radial vibration peak at one times running speed.
A building maintenance manager wants to reduce PM labor without increasing failures. Which approach best fits this goal?
Answer: Shift time-based tasks with random failure patterns to condition-based monitoring
Time-based PM is ineffective for random failures, so condition-based tasks reduce wasted labor while still catching problems.
Which metric expresses the percentage of scheduled PM work orders completed within their allowed time window?
Answer: PM compliance
PM compliance measures how many scheduled PMs were completed on time versus scheduled.
A commonly used grace-period rule for PM compliance allows completion within what portion of the PM interval?
Answer: Within 10% of the interval
Many organizations use a 10% rule, so a 30-day PM must be completed within about 3 days of its due date.
How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- learn.nahro.org — Eligibility, fees, score validity · verified Oct 2026
- nahro.org — Renewal, retake policy · verified Oct 2026