  1. Pump A costs $8,000 with $3,000 annual energy costs; Pump B costs $11,000 with $2,000 annual energy costs. Over a 10-year life (ignoring discounting), which is the better choice?

    Answer: Pump B, because its total 10-year cost is $31,000 vs. $38,000

    Pump A totals $8,000 + $30,000 = $38,000 while Pump B totals $11,000 + $20,000 = $31,000.

  2. What is a rolling forecast in facility budgeting?

    Answer: A forecast updated regularly to always project a fixed period ahead

    Rolling forecasts are refreshed periodically, such as quarterly, to keep a consistent forward-looking window.

  3. An $80,000 efficiency project qualifies for a $20,000 utility rebate and saves $15,000 per year. What is the simple payback after the rebate?

    Answer: 4 years

    Net cost is $80,000 - $20,000 = $60,000, and $60,000 / $15,000 = 4 years.

  4. Which cost is most likely to be variable in a facility operating budget?

    Answer: Janitorial supplies that increase with building occupancy

    Variable costs rise and fall with activity levels such as occupancy or usage.

  5. What should a monthly budget variance report include beyond the numbers?

    Answer: Explanations of significant variances and planned corrective actions

    Variance reports are useful to management when they explain causes and responses for major deviations.

  6. An annual operating budget for a maintenance department typically covers which period?

    Answer: One fiscal year

    Operating budgets fund recurring expenses over a single fiscal year.

  7. What is a sinking fund in facility financial management?

    Answer: Money set aside periodically to pay for a future replacement or obligation

    Sinking funds accumulate regular contributions so major future costs can be paid without borrowing.

How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. learn.nahro.org — Eligibility, fees, score validity · verified Oct 2026
  2. nahro.org — Renewal, retake policy · verified Oct 2026