  1. A roof costs $200,000 to replace, has a 25-year useful life, and is 10 years old. What is its fully funded balance?

    Answer: $80,000

    Fully funded balance = current replacement cost × (effective age ÷ useful life), so $200,000 × 10/25 = $80,000.

  2. An association has $150,000 in reserves and a total fully funded balance of $300,000. What is its percent funded?

    Answer: 50%

    Percent funded = actual reserve balance ÷ fully funded balance, so $150,000 ÷ $300,000 = 50%.

  3. Under the CAI National Reserve Study Standards, which item would generally NOT qualify as a reserve component?

    Answer: Pool chemicals purchased monthly

    Recurring monthly supplies have no predictable multi-year remaining life and belong in the operating budget.

  4. Which reserve study level of service includes a component inventory, condition assessment, life and valuation estimates, fund status, and funding plan?

    Answer: Full reserve study

    A full study is the only level that establishes the component inventory from scratch along with all other tasks.

  5. A reserve funding plan that aims to keep the reserve balance just above zero is known as what?

    Answer: Baseline funding

    Baseline funding keeps the cash balance above zero over the projection period, with the highest risk of shortfalls.

  6. The board wants a funding goal of keeping reserves at a set target such as 70% funded. Which funding method is this?

    Answer: Threshold funding

    Threshold funding keeps the balance above a specified dollar amount or percent funded chosen by the board.

  7. A manager notices utility costs are 18% over budget at midyear. What is the BEST first step?

    Answer: Perform a variance analysis to identify the cause

    Variance analysis explains why actuals differ from budget so the board can make an informed response.

How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. camicb.org — Eligibility, exam format, retake fee · verified Oct 2026
  2. camicb.org — Test delivery, fees, passing score · verified Oct 2026