  1. Which project management framework is most commonly recommended in CMC consulting engagements for iterative client deliverables?

    Answer: Agile/Scrum

    Agile/Scrum is preferred for consulting engagements requiring iterative feedback and adaptable deliverables.

  2. A CMC consultant is managing scope creep on a client project. What is the FIRST recommended action?

    Answer: Document the change request and assess impact on timeline and cost

    Documenting and impact-assessing change requests maintains transparency and protects both the consultant and client.

  3. In CMC project delivery, a RACI matrix is used primarily to:

    Answer: Clarify roles and responsibilities across stakeholders

    A RACI matrix defines who is Responsible, Accountable, Consulted, and Informed for each task.

  4. Which metric best indicates whether a consulting project is on schedule according to earned value management?

    Answer: Schedule Performance Index (SPI)

    SPI measures schedule efficiency by comparing earned value to planned value.

  5. A CMC consultant conducts a post-project review primarily to:

    Answer: Capture lessons learned and improve future engagements

    Post-project reviews capture lessons learned that improve methodology and client outcomes on future engagements.

  6. When a consulting project milestone is at risk, a CMC consultant should FIRST:

    Answer: Identify root causes and develop mitigation options before communicating to the client

    Identifying root causes and preparing mitigation options enables a proactive, solution-oriented conversation with the client.