Which of the following best describes a work breakdown structure (WBS) in a consulting project?
Answer: A hierarchical decomposition of total project scope into manageable components
A WBS hierarchically decomposes project scope into smaller, manageable work packages.
In CMC engagements, the critical path method (CPM) is used to:
Answer: Identify the sequence of tasks that determines the minimum project duration
CPM identifies the longest sequence of dependent tasks, determining the shortest possible project duration.
A CMC consultant should define project success criteria at which phase of the engagement?
Answer: During project initiation and scoping
Defining success criteria during initiation ensures client and consultant alignment before work begins.
What is the purpose of a project steering committee in a consulting engagement?
Answer: To provide strategic oversight, approve major decisions, and resolve escalations
A steering committee provides governance-level oversight and resolves issues that exceed the project team's authority.
Which risk response strategy involves transferring project risk to a third party?
Answer: Risk transfer
Risk transfer shifts the financial or operational impact of a risk to another party, such as through insurance or subcontracting.
A CMC consultant's project status report should include all of the following EXCEPT:
Answer: Confidential competitor intelligence
Confidential competitor intelligence is not appropriate for client project status reports due to legal and ethical constraints.