  1. When installing a prehung exterior door, which jamb is normally set plumb and fastened first?

    Answer: Hinge jamb

    The hinge jamb carries the door, so it is set plumb first and the rest of the frame is adjusted to the slab.

  2. What is a typical consistent reveal (gap) between an exterior door slab and its jamb?

    Answer: 1/8 in.

    About 1/8 in. all around lets the door swing freely while weatherstripping seals the gap.

  3. What security feature should an outswing exterior door's hinges have?

    Answer: Non-removable hinge pins

    Outswing hinge pins are exposed on the outside, so non-removable pins stop someone from pulling them and taking the door off.

  4. What is the purpose of kick-out (diverter) flashing where a roof eave meets a sidewall?

    Answer: To send roof runoff into the gutter and away from the wall cladding

    Kick-out flashing stops water from running behind the siding at the bottom of a roof-wall joint, a common source of rot.

  5. What is the preferred way to cut fiber cement siding to control respirable crystalline silica exposure?

    Answer: Fiber cement shears or a saw with a dust-collection system

    OSHA's silica standard favors shears, scoring, or saws with dust collection to limit silica dust.

  6. How should butt joints in fiber cement lap siding be handled?

    Answer: Backed with joint flashing or placed over framing per the manufacturer

    Manufacturers call for butt joints to be flashed behind (or set on framing) so water at the joint does not reach the WRB.

  7. Which foam should be used to seal the gap between a window frame and the rough opening?

    Answer: Low-expansion foam made for windows and doors

    Low-expansion foam seals the gap without pushing on and bowing the frame, which would make the sash bind.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. nari.org — Test delivery, passing score, retake policy, score release, test dates, eligibility, fees, exam format, retake fee, time limit · verified Nov 2026
Exterior Cladding, Windows & Doors Installation Flashcards — CLC Study Cards with Answers