Practice Test Geeks home

Civil Engineering PE Project Planning and Estimating 4

A contractor uses the 50-50 rule for earned value on in-progress work packages.
If 8 of 20 work packages are complete, 4 are in progress, and 8 have not started, what is the earned value percentage of planned value?