Project Planning and Estimating Flashcards

7 cards from real Civil Engineering PE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Planning and Estimating flashcards as text
  1. A project has the following activities with durations: A=5d, B=3d, C=4d, D=6d, E=2d. The network shows A→C→E and A→B→D→E as paths. What is the critical path duration?

    Answer: 16 days

    Path A→B→D→E = 5+3+6+2 = 16 days, which is longer than A→C→E = 5+4+2 = 11 days, making it the critical path.

  2. Which estimating method uses historical cost data from similar completed projects as its primary basis?

    Answer: Analogous estimating

    Analogous estimating relies on actual cost data from previous similar projects to estimate future project costs.

  3. A contractor submits a bid of $2,400,000 for a project. If the contractor's overhead is 12% and profit is 8% of the total bid, what is the estimated direct cost?

    Answer: $1,920,000

    Direct cost = $2,400,000 × (1 - 0.12 - 0.08) = $2,400,000 × 0.80 = $1,920,000.

  4. In earned value management, a project has BAC=$500,000, EV=$300,000, AC=$350,000. What is the Cost Performance Index (CPI)?

    Answer: 0.86

    CPI = EV/AC = $300,000/$350,000 ≈ 0.86, indicating the project is over budget.

  5. The Master Format specification system used in construction is organized primarily by:

    Answer: Work results and construction products

    MasterFormat organizes specifications by work results and construction products, providing a standard numbering system for construction documents.

  6. What does a negative float (slack) on a non-critical activity indicate in a project schedule?

    Answer: The project cannot meet its deadline without changes

    Negative float indicates the project schedule is infeasible and cannot meet its imposed deadline without compressing activities or adding resources.

  7. A construction project uses a unit price contract for earthwork at $8.50/CY. If the estimated quantity is 50,000 CY but the actual quantity is 62,000 CY, what is the final payment for earthwork?

    Answer: $527,000

    Final payment = actual quantity × unit price = 62,000 CY × $8.50/CY = $527,000.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ncees.org — Passing score, retake policy, score validity, test delivery, eligibility, fees, exam format, score release, test dates · verified Nov 2026