Specialist Safety Regulations Flashcards

6 cards from real CITB SPECIALISTS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Specialist Safety Regulations flashcards as text
  1. Under the Construction (Design and Management) Regulations 2015, who has the primary duty to plan, manage, and monitor the construction phase on a project with more than one contractor?

    Answer: The principal contractor

    Under CDM 2015, the principal contractor is responsible for planning, managing, monitoring, and coordinating the construction phase when there is more than one contractor. The client appoints them, but the day-to-day management duty falls on the principal contractor.

  2. What is the maximum period a specialist contractor can work at height from a mobile elevating work platform (MEWP) before a written rescue plan must be in place?

    Answer: There is no grace period; a rescue plan must always be in place before work begins

    The Work at Height Regulations 2005 require that a rescue plan is in place before any work at height begins, including MEWP operations. There is no grace period — rescue arrangements must be planned and ready from the outset.

  3. A specialist supervisor discovers that a subcontractor's operatives do not hold valid CSCS cards. What is the correct course of action?

    Answer: Stop the operatives from working and report the issue to the principal contractor

    CSCS cards verify that workers have the required training and qualifications. Operatives without valid cards should not be permitted to work on site. The specialist supervisor must stop the work and escalate the matter to the principal contractor for resolution.

  4. Which regulation specifically requires employers to carry out noise assessments where specialist operations may expose workers to harmful noise levels?

    Answer: The Control of Noise at Work Regulations 2005

    The Control of Noise at Work Regulations 2005 specifically require employers to assess noise exposure, provide hearing protection, and implement noise control measures. The lower exposure action value is 80 dB(A) and the upper value is 85 dB(A).

  5. Under RIDDOR 2013, which of the following incidents involving a specialist contractor must be reported to the HSE?

    Answer: A worker is incapacitated for more than 7 consecutive days due to a work-related injury

    Under RIDDOR 2013, an over-7-day incapacitation (where a worker is unable to perform their normal duties for more than 7 consecutive days, not counting the day of the accident) must be reported to the HSE. Minor injuries and near-misses without specified dangerous occurrences do not require RIDDOR reporting.

  6. What must a specialist supervisor ensure is in place before any hot work (welding, cutting, grinding) begins on a construction site?

    Answer: A hot work permit with fire watch arrangements

    Hot work requires a formal hot work permit system that identifies the hazards, control measures, and fire watch arrangements. A fire watch must be maintained during and for a specified period after the work to detect any smouldering materials. Verbal agreements alone are insufficient.

How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. citb.co.uk — Fees, registration deadline, test delivery, retake policy, score release, exam format, passing score, time limit, exam information · verified Oct 2026
  2. cscs.uk.com — Eligibility, score validity · verified Oct 2026