Before any demolition work begins on a structure, what must a specialist demolition contractor produce under UK regulations?
Answer: A written demolition method statement based on a structural survey
BS 6187 and CDM 2015 require that a written method statement is produced before demolition begins, based on a thorough structural survey of the building. This must detail the sequence of demolition, precautions, exclusion zones, and emergency procedures. The method statement must be prepared by a competent person.
When demolishing a building that may contain asbestos, what must a specialist contractor do before any physical demolition work starts?
Answer: Commission a Refurbishment and Demolition Asbestos Survey (Type 3) before work begins
The Control of Asbestos Regulations 2012 require a Refurbishment and Demolition Survey before demolition begins. This is a destructive inspection that identifies all asbestos-containing materials (ACMs) so they can be removed by a licensed contractor before demolition proceeds. Proceeding without this survey is a criminal offence.
What is the primary purpose of establishing an exclusion zone during specialist demolition operations?
Answer: To protect the public and workers from falling debris, dust, and structural collapse
Exclusion zones are established to prevent unauthorised persons from entering areas where they could be struck by falling debris, exposed to hazardous dust, or endangered by uncontrolled structural collapse. The size of the zone depends on the height of the structure and the demolition method being used.
During the deliberate collapse of a structure using pre-weakening techniques, who must be in overall control of the operation?
Answer: A competent person appointed specifically to control the demolition sequence
Pre-weakening and deliberate collapse are among the highest-risk demolition techniques. A specifically appointed competent person must maintain overall control, ensuring the sequence proceeds as planned, all personnel are at safe distances, and the collapse direction is as engineered. This person must have specific demolition experience and qualifications.
What is the correct approach to managing services (gas, electric, water) before specialist demolition of a building?
Answer: Confirm disconnection with each utility provider and obtain written confirmation before work starts
All services must be identified, disconnected, and capped at the boundary by the relevant utility companies. Written confirmation of disconnection must be obtained and kept on site. Simply turning off at the mains is insufficient — mains supplies can be inadvertently restored, and underground services may be pressurised.
A specialist demolition supervisor notices that an adjacent occupied building shares a party wall with the structure being demolished. What additional measures are required?
Answer: A structural assessment of the party wall, temporary support measures, and a monitoring programme
Where a party wall or shared structure exists, a structural engineer must assess the wall's condition and the impact of demolition on the adjacent building. Temporary support (shoring, propping) may be required, and monitoring (crack gauges, survey points) must be established to detect movement. The Party Wall etc. Act 1996 also applies.
How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- citb.co.uk — Fees, registration deadline, test delivery, retake policy, score release, exam format, passing score, time limit, exam information · verified Oct 2026
- cscs.uk.com — Eligibility, score validity · verified Oct 2026