Risk Assessment and Method Statements Flashcards

6 cards from real CITB MANAGERS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Risk Assessment and Method Statements flashcards as text
  1. Under the Management of Health and Safety at Work Regulations 1999, when must a risk assessment be reviewed?

    Answer: When there is reason to believe it may no longer be valid, or when a significant change in the matters it relates to has occurred

    A risk assessment must be reviewed when there is reason to believe it is no longer valid (e.g., following an incident) or when a significant change has occurred in the work, environment, or workforce. There is no mandatory fixed review interval.

  2. What is the five-step approach to risk assessment recommended by the HSE?

    Answer: Identify hazards; identify who might be harmed and how; evaluate risks and implement controls; record findings; review and update

    The HSE's five steps are: (1) Identify hazards; (2) Decide who might be harmed and how; (3) Evaluate risks and decide on controls; (4) Record findings and implement; (5) Review the assessment and update if necessary.

  3. A 'suitable and sufficient' risk assessment must:

    Answer: Identify significant risks and introduce adequate controls proportionate to the risk — the level of detail must be appropriate to the nature and complexity of the risk

    A suitable and sufficient risk assessment identifies significant risks, not trivial ones, and the controls introduced are proportionate to the risk level. The level of detail must be appropriate — more complex and higher-risk activities require more detailed assessments.

  4. What is the hierarchy of controls and what position does PPE occupy within it?

    Answer: Elimination, substitution, engineering controls, administrative controls, PPE — PPE is the last resort

    The hierarchy of controls (in order of preference): (1) Eliminate the hazard; (2) Substitute a less hazardous option; (3) Engineering controls; (4) Administrative controls (procedures, training, supervision); (5) PPE as the last resort. PPE protects the worker but does not remove the hazard.

  5. A risk assessment identifies a high risk. What should the employer's first priority be?

    Answer: Eliminate the hazard entirely if reasonably practicable — if not, apply further controls to reduce the risk to an acceptable level

    When a high risk is identified, the employer's first obligation is to try to eliminate the hazard (top of the hierarchy). Only if elimination is not reasonably practicable should they apply engineering controls, administrative controls, and PPE in that order.

  6. A risk assessment that covers a generic work activity (rather than a site-specific one) is called a:

    Answer: Generic risk assessment (GRA) — to be supplemented with site-specific adaptations

    A Generic Risk Assessment covers a standard activity as normally performed. It must be reviewed and supplemented with site-specific information before use on any particular site, as local conditions may introduce additional or different risks.

How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. citb.co.uk — Retake policy, score release, exam format, passing score, time limit, test delivery, eligibility, fees · verified Oct 2026
Risk Assessment and Method Statements Flashcards — CITB MANAGERS Study Cards with Answers