← All CITB MANAGERS Flashcard Decks

Risk Assessment and Method Statements Flashcards

6 cards from real CITB MANAGERS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Risk Assessment and Method Statements flashcards as text
  1. A contractor submits a method statement that does not adequately address a specific risk on site. The principal contractor should:

    Answer: Refuse to allow the work to start and require the method statement to be revised and resubmitted before the activity commences

    If a method statement is inadequate, the principal contractor must not allow the work to proceed. The contractor must revise the document to adequately address the identified risks and have it approved before starting. Proceeding with an inadequate RAMS creates legal liability.

  2. Competent persons who carry out risk assessments must have:

    Answer: Sufficient knowledge, training, experience, and understanding of the work to carry out an assessment that is suitable and sufficient

    Competence to carry out risk assessments requires knowledge of the work activity and the hazards it involves, understanding of risk assessment methodology, and the experience to make sound judgements. There is no mandatory specific qualification, but relevant training is important.

  3. What is the purpose of a 'pre-task' or 'point of work' risk assessment?

    Answer: A brief review immediately before starting a task, checking that conditions match the RAMS assumptions and identifying any additional site-specific hazards

    A pre-task (or point-of-work) risk assessment is a brief check immediately before starting work to confirm that site conditions match the assumptions in the RAMS, identify any additional hazards not covered, and confirm that all required controls are in place.

  4. Which regulation requires employers to appoint one or more 'competent persons' to assist with health and safety?

    Answer: The Management of Health and Safety at Work Regulations 1999, Regulation 7

    Regulation 7 of the Management of Health and Safety at Work Regulations 1999 requires employers to appoint one or more competent persons to assist in undertaking the measures they need to comply with health and safety law.

  5. A risk assessment for excavation work must consider which specific additional factors compared to general construction risk?

    Answer: The presence of underground services, risk of ground collapse, risk of flooding, and any confined space elements

    Excavation-specific risk factors include: buried services (identification and protection), ground collapse (stability assessment, shoring requirements), flooding/groundwater, presence of confined space hazards (oxygen deficiency, toxic gases), and stability of adjacent structures.

  6. When a risk assessment is recorded, the significant findings must include:

    Answer: The hazards, who is at risk, existing controls, residual risk level, and any further actions required

    Significant findings must record: the hazards identified, who might be harmed, the existing controls in place, the level of residual risk, and any further control measures that need to be implemented. This provides a clear and actionable record.

How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. citb.co.uk — Retake policy, score release, exam format, passing score, time limit, test delivery, eligibility, fees · verified Oct 2026