Permit to Work Systems Flashcards
6 cards from real CITB MANAGERS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Permit to Work Systems flashcards as text
The permit to work system for excavation near buried services must ensure:
Answer: Service locations have been confirmed by survey, a cable avoidance tool has been used, hand-digging exclusion zones around known services are specified, and emergency procedures are in place if a service is struck
A permit for excavation near services must: confirm service locations have been verified using plans and CAT equipment, specify the hand-dig exclusion zones, identify the emergency procedure if a service is struck, and confirm who to contact (gas emergency, electricity network operator) in an emergency.
Why must only one permit to work be active at a time for a specific piece of equipment or work location?
Answer: To prevent conflicting authorisations that could result in simultaneous operations creating hazards — each piece of equipment or work area can only be under one set of permit conditions at a time
Multiple simultaneous permits for the same equipment or location can result in conflicting instructions and dangerous situations (e.g., one permit assumes an isolation is in place; another permits that isolation to be removed). One permit per location/equipment prevents such conflicts.
A permit to work for roof work should specify:
Answer: The edges to be protected, the access arrangements, the load-bearing capacity of the roof, the weather conditions under which work may not proceed, the fall protection equipment required, and rescue arrangements
A roof work PTW must specify: edge protection requirements, safe access routes, roof load-bearing capacity (especially for fragile or older roofs), weather restrictions (wind speed, rain), fall protection equipment, and how a worker who falls will be rescued.
What is a 'sign-on, sign-off' system in relation to permits to work?
Answer: A system where each worker entering the permit-controlled area signs on at the start of the permit and signs off at completion, confirming they were present and have left the area safely
A sign-on, sign-off system ensures that every person who enters a permit-controlled area is accounted for at all times. At permit close-out, checking that all workers have signed off confirms no one is left in a confined space, hazardous area, or isolated zone.
A site operative asks the site manager if they can carry out work covered by a permit to work without the permit, as it 'will only take five minutes'. The site manager should:
Answer: Refuse — permit requirements apply regardless of the duration of the task. The permit ensures precautions are in place even for brief high-risk activities
The duration of a task does not determine whether a permit is needed — the risk level does. Many catastrophic incidents have occurred during brief 'five-minute jobs' without permits. The permit process ensures precautions are in place even for short tasks.
How does a permit to work contribute to the prevention of accidents during maintenance of plant and equipment?
Answer: By ensuring that plant is safely isolated (locked and tagged) before maintenance begins, and that it cannot be accidentally re-energised while workers are inside or working on it
Energy isolation is the critical protection for maintenance workers. A PTW for plant maintenance confirms that all energy sources (electrical, pneumatic, hydraulic) are safely isolated and locked off (LOTO — lock out, tag out), preventing accidental start-up or re-energisation while workers are exposed.
How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- citb.co.uk — Retake policy, score release, exam format, passing score, time limit, test delivery, eligibility, fees · verified Oct 2026