During a post-implementation review, an IS auditor finds that user acceptance testing (UAT) was bypassed due to project deadline pressure. What is the PRIMARY risk?
-
A
Budget overruns in future phases
-
B
Undiscovered defects may reach production
-
C
Development team morale decreases
-
D
Project documentation becomes incomplete