An organization is preparing to migrate data from a legacy system to a new ERP platform. Which of the following is the MOST critical control for an IS auditor to verify before the data conversion process begins?
-
A
The new ERP system's user acceptance testing (UAT) has been successfully completed.
-
B
A complete data backup of the legacy system has been performed and validated.
-
C
The data conversion logic has been reviewed and approved by the data owners.
-
D
End-user training on the new ERP system has been concluded.