During a project, a client frequently changes requirements without formal documentation. What should the CID do?
-
A
Accept all changes verbally to keep the client happy
-
B
Implement a change order process that documents and approves all scope changes in writing
-
C
Stop the project until the client stops making changes
-
D
Only implement changes that seem technically feasible