What is the purpose of a 'contingency plan' required for large quantity generator hazardous waste storage areas?
-
A
To outline procedures for managing waste when storage capacity is exceeded
-
B
To describe emergency response actions for fires, explosions, or unplanned releases
-
C
To provide backup labeling procedures if original labels are lost
-
D
To schedule routine container inspections and aisle maintenance