  1. According to NIST SP 800-61, which of the following is the CORRECT sequence of phases in an incident response lifecycle?

    Answer: Preparation → Detection and Analysis → Containment, Eradication, and Recovery → Post-Incident Activity

    NIST SP 800-61 defines four incident response phases: Preparation; Detection and Analysis; Containment, Eradication, and Recovery; and Post-Incident Activity (which includes the lessons-learned process). The other sequences mix elements of different frameworks or incorrectly order the phases.

  2. What is the key distinction between a Contingency Plan and a Disaster Recovery Plan (DRP)?

    Answer: A Contingency Plan covers all types of disruptions to information systems, while a DRP focuses specifically on recovering IT systems after a major disaster

    Per NIST SP 800-34, a Contingency Plan is a broader document covering a range of disruptive events affecting information systems. A Disaster Recovery Plan is a subset that specifically addresses recovery of IT infrastructure following a major disaster. The Contingency Plan may reference or incorporate the DRP.

  3. An organization's management states that their critical payroll system must be restored to full operation within 4 hours of a disruption. This requirement is BEST described as which of the following?

    Answer: Recovery Time Objective (RTO)

    The Recovery Time Objective (RTO) defines the maximum acceptable length of time that a system can be offline after a disruption. The RPO defines how much data loss is acceptable (measured in time). MTD is the absolute maximum time a business function can be unavailable before mission failure. MTTR is a reliability metric for average repair time.

  4. During a contingency plan test, an organization uses actual production data and physically shuts down the primary data center, requiring IT staff to activate the alternate site. This type of test is BEST described as which of the following?

    Answer: Full interruption test

    A full interruption test (also called a full-scale test) involves actually shutting down the primary system and activating the backup/alternate site, making it the most realistic but also most disruptive and risky test type. A parallel test runs both sites simultaneously. A tabletop exercise is discussion-based. A structured walk-through reviews the plan without operational activation.

  5. Which NIST Special Publication provides the primary guidance for developing and testing contingency plans for federal information systems?

    Answer: NIST SP 800-34

    NIST SP 800-34, 'Contingency Planning Guide for Federal Information Systems,' is the primary reference for developing, testing, and maintaining contingency plans. SP 800-53 contains the security control catalog (including CP controls), SP 800-61 covers incident response, and SP 800-137 covers continuous monitoring.

  6. After a cybersecurity incident is resolved, an organization conducts a post-incident review. Which of the following outcomes represents the MOST valuable result of this activity from a risk management perspective?

    Answer: Identifying lessons learned that can be used to improve detection capabilities, response procedures, and preventive controls

    The post-incident activity phase focuses on identifying lessons learned to improve the organization's security posture going forward — updating detection tools, refining response playbooks, and strengthening preventive controls. While cost calculation and system restoration verification are valid activities, the primary risk management value is the organizational learning that reduces likelihood or impact of future incidents.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. isc2.org — Test delivery, eligibility, passing score, time limit, renewal, score validity, score release, fees, exam information · verified Nov 2026