A buyer receives two fastener quotes: Supplier A offers $0.08/piece with a 10-week lead time; Supplier B offers $0.11/piece with a 3-week lead time. Which factor most justifies choosing Supplier B despite the higher unit price?
-
A
Lower total cost of ownership when carrying costs are considered
-
B
Supplier B uses a better coating process
-
C
Supplier A is located overseas
-
D
Supplier B has ISO 9001 certification