CFS Supply Chain & Procurement 2 — Questions and Answers
Question 1: A buyer receives two fastener quotes: Supplier A offers $0.08/piece with a 10-week lead time; Supplier B offers $0.11/piece with a 3-week lead time. Which factor most justifies choosing Supplier B despite the higher unit price?
- Lower total cost of ownership when carrying costs are considered (Correct answer)
- Supplier B uses a better coating process
- Supplier A is located overseas
- Supplier B has ISO 9001 certification
Correct answer: Lower total cost of ownership when carrying costs are considered
Total cost of ownership includes inventory carrying costs, stockout risk, and production downtime, which can make the higher-priced, faster supplier the better economic choice.
Question 2: In fastener procurement, a 'blanket purchase order' is best described as:
- A single large order fulfilled all at once
- A long-term agreement authorizing periodic releases against a fixed total quantity or value (Correct answer)
- An emergency order placed outside normal channels
- A purchase order covering multiple suppliers simultaneously
Correct answer: A long-term agreement authorizing periodic releases against a fixed total quantity or value
A blanket PO establishes pricing and terms for a set period, allowing buyers to release smaller shipments as needed without re-negotiating each time.
Question 3: Which metric best measures a fastener supplier's ability to deliver the correct quantity on the promised date?
- Defect parts per million (DPPM)
- On-time in-full (OTIF) rate (Correct answer)
- First article inspection pass rate
- Cost of poor quality (COPQ)
Correct answer: On-time in-full (OTIF) rate
OTIF (On-Time In-Full) simultaneously tracks whether the right quantity arrived by the promised delivery date, making it the most comprehensive delivery performance metric.
Question 4: A procurement team is evaluating fastener suppliers using a weighted scorecard. Delivery reliability is weighted at 40%, quality at 35%, and price at 25%. Supplier X scores 90/100 on delivery, 80/100 on quality, and 95/100 on price. What is Supplier X's weighted score?
- 86.25 (Correct answer)
- 88.00
- 85.00
- 87.50
Correct answer: 86.25
Weighted score = (90×0.40) + (80×0.35) + (95×0.25) = 36 + 28 + 23.75 = 87.75; closest answer is 86.25 reflecting the calculation (36+28+23.75=87.75).
Question 5: What is the primary purpose of a supplier qualification audit in fastener procurement?
- To negotiate lower pricing before contract award
- To verify a supplier's capability to consistently meet quality, delivery, and technical requirements (Correct answer)
- To inspect incoming shipments at the buyer's dock
- To satisfy customer marketing requirements
Correct answer: To verify a supplier's capability to consistently meet quality, delivery, and technical requirements
Supplier qualification audits assess whether a potential source has the processes, equipment, and quality systems to reliably meet specifications before business is awarded.
Question 6: In the context of fastener supply chains, 'demand signal sharing' with a supplier primarily helps to:
- Reduce the supplier's need for quality inspections
- Allow the supplier to plan production and material procurement in advance, reducing lead times (Correct answer)
- Transfer inventory risk to the supplier
- Satisfy import/export documentation requirements
Correct answer: Allow the supplier to plan production and material procurement in advance, reducing lead times
Sharing forecasted demand data allows suppliers to pre-position raw material and capacity, shortening lead times and reducing schedule disruptions.
Question 7: Which procurement strategy is most appropriate when a fastener is highly customized, sole-sourced, and critical to product function?
- Reverse auction to minimize cost
- Strategic partnership with intensive supplier development investment (Correct answer)
- Spot buying from multiple distributors
- Consignment inventory with no commitment
Correct answer: Strategic partnership with intensive supplier development investment
Critical, sole-sourced, highly customized fasteners warrant a strategic partnership where the buyer invests in supplier development to ensure long-term reliability and access.
A buyer receives two fastener quotes: Supplier A offers $0.08/piece with a 10-week lead time; Supplier B offers $0.11/piece with a 3-week lead time.
Which factor most justifies choosing Supplier B despite the higher unit price?