  1. Under 44 CFR 60.3, what elevation must a community obtain and keep on record for every new or substantially improved structure in the Special Flood Hazard Area?

    Answer: The as-built elevation of the lowest floor, including any basement

    Communities must record the as-built lowest floor elevation (or the floodproofed elevation) of new and substantially improved structures.

  2. Section 1316 of the National Flood Insurance Act lets FEMA do what with a structure that a state or local authority has declared in violation of floodplain laws?

    Answer: Deny flood insurance coverage for that structure

    Section 1316 lets FEMA deny flood insurance to a property the local or state authority has formally declared to be in violation.

  3. What is the main purpose of a Community Assistance Visit (CAV)?

    Answer: To assess the community's floodplain management program and give technical assistance

    A CAV is an on-site review of how the community administers its floodplain program, with help to fix any deficiencies.

  4. Which of these is NOT a required condition for granting a variance under 44 CFR 60.6?

    Answer: The applicant's financial hardship of meeting the requirements

    Variances must be based on hardship tied to the property itself; the owner's financial or personal hardship does not qualify.

  5. A remodel is considered a substantial improvement when its cost equals or exceeds what percentage of the structure's market value before the work starts?

    Answer: 50 percent

    NFIP regulations define substantial improvement as work costing 50% or more of the structure's pre-improvement market value.

  6. Under 44 CFR 60.6, when a variance allows a lowest floor below the BFE, the applicant must be told in writing that flood insurance premiums could go as high as:

    Answer: $25 per $100 of coverage

    The regulation requires written notice that premiums may reach $25 per $100 of insurance coverage.

  7. Which body must legally adopt the floodplain management regulations a community needs to take part in the NFIP?

    Answer: The community's governing body

    NFIP participation is voluntary, and the local governing body has to adopt and enforce the regulations.

  8. What is the main financial consequence when FEMA places a community on probation?

    Answer: A surcharge is added to every flood insurance policy in the community

    Probation adds a $50 surcharge to each NFIP policy in the community to push it to fix program deficiencies.

  9. If a community is suspended from the NFIP, what happens?

    Answer: New and renewed NFIP flood insurance is not available in the community

    Suspension ends the sale and renewal of NFIP policies and restricts federal financial help for SFHA construction.

  10. Under 44 CFR 65.3, how soon must a community notify FEMA of physical changes that affect base flood elevations?

    Answer: As soon as practicable, but within 6 months

    Communities must submit technical or scientific data on BFE changes as soon as practicable, and no later than six months after the information becomes available.

  11. When calculating market value for a substantial improvement or substantial damage determination, which value should be used?

    Answer: Structure only, excluding the land

    Market value for SI/SD covers only the structure, never the land.

  12. Which activity counts as 'development' under the NFIP and requires a floodplain permit in the SFHA?

    Answer: Placing fill to raise a building site

    Development includes filling, grading, paving, excavation, dredging, mining, and storing equipment or materials, as well as buildings.

  13. Before issuing a floodplain development permit, the floodplain administrator must make sure the applicant has:

    Answer: Got all required federal, state, and local permits, such as a Clean Water Act Section 404 permit

    44 CFR 60.3(a)(2) requires review to confirm all other necessary government permits have been obtained.

  14. Before a community allows a watercourse to be altered or relocated, the NFIP requires it to:

    Answer: Notify adjacent communities and the state coordinating agency and send evidence to FEMA

    44 CFR 60.3(b)(6) requires notifying neighboring communities and the state, submitting evidence to FEMA, and keeping the channel's flood-carrying capacity.

  15. Who is authorized to certify the elevation information on a FEMA Elevation Certificate?

    Answer: A licensed land surveyor, engineer, or architect authorized by state law

    Only professionals licensed and authorized under state law to certify elevations may complete the elevation sections of the EC.

  16. In the Community Rating System, a Class 5 community gets what premium discount on policies in the SFHA?

    Answer: 25 percent

    Each CRS class step is worth 5%, so Class 5 gets 25% off in the SFHA.

  17. Which is a basic requirement for a community to take part in the Community Rating System?

    Answer: It must be in the Regular Program of the NFIP and in full compliance

    CRS is voluntary but open only to Regular Program communities that are in full compliance with NFIP requirements.

  18. What is the NFIP Emergency Program?

    Answer: The first phase of participation, offering limited coverage before a detailed FIRM is issued

    The Emergency Program gives limited amounts of insurance until FEMA finishes a detailed study and the community joins the Regular Program.

  19. After FEMA issues a Letter of Final Determination for a new FIRM, how long does the community usually have to adopt compliant floodplain regulations?

    Answer: 6 months

    The compliance period between the LFD and the map's effective date is six months.

  20. Under 44 CFR 60.3(d)(3), before allowing encroachments in a designated regulatory floodway, the community must have an engineering analysis showing:

    Answer: The encroachment would cause no increase in the base flood elevation

    Floodway encroachments must be shown, through hydrologic and hydraulic analysis, to cause no increase in flood levels during the base flood.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. illinoisfloods.org — Fees, test delivery, exam information · verified Nov 2026
  2. floods.org — Late registration, eligibility, fees, exam format, passing score, renewal, retake fee, retake policy, score release, time limit · verified Nov 2026