Project Management & Execution Flashcards

7 cards from real CFM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Management & Execution flashcards as text
  1. To compress a schedule, a team starts building the output dashboards while the calculation engine is still being finalized. What technique is this?

    Answer: Fast-tracking

    Fast-tracking runs normally sequential tasks in parallel, which saves time but raises rework risk.

  2. Adding two more analysts to critical-path tasks to shorten the project is known as:

    Answer: Crashing

    Crashing adds resources to critical-path activities to cut duration, usually at extra cost.

  3. What is the main purpose of a lessons-learned session at the close of a modeling project?

    Answer: To capture what worked and what didn't so that future projects improve

    Documenting lessons learned builds organizational knowledge and improves estimates, templates, and processes.

  4. Which practice gives the strongest audit trail for changes made to a model after review?

    Answer: A dated change log listing each change, its reason, its author, and the affected sheets

    A structured change log lets reviewers trace and re-test every modification.

  5. What does a Work Breakdown Structure (WBS) do in a modeling project?

    Answer: Breaks the total project scope into smaller, manageable deliverables and work packages

    A WBS decomposes the scope hierarchically, which supports estimating, assigning, and tracking work.

  6. Which practice best ensures that model inputs can be validated during execution?

    Answer: Recording the source, date, and owner of every key input in the assumptions sheet

    Documented sources let reviewers and stakeholders verify inputs and update them reliably.

  7. The status report shows a model on schedule, but testing has not started and is planned for the final day. What is the main project risk?

    Answer: Too little time to fix errors found late, putting quality or the deadline at risk

    Squeezing testing into the end leaves no buffer for fixes, so integrated, ongoing testing is better practice.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. fminstitute.com — Test delivery, exam dates, exam format, time limit, retake policy, score validity, registration deadline, retake fee, eligibility, fees · verified Nov 2026